Raytheon's Development and Testing on Track for DDG 51 Flight III


Reading time ( words)

Raytheon Company announced its AN/SPY-6(V) Air and Missile Defense Radar (AMDR)team has completed the first full radar array, fully populated with component Line Replaceable Units (LRUs), including more than 5,000 Transmit/Receive elements, in 140 days. In less than two years, the radar has been designed, built and transitioned to test; the Engineering and Manufacturing Development (EMD) phase of the program is now more than 66 percent complete. The program remains on track to begin production and deliver on time to the FY16 authorized DDG 51 Flight III destroyer.

"As each milestone is completed, development of the SPY-6 radar progresses on schedule," said U.S. Navy Captain Seiko Okano, major program manager, Above Water Sensors (IWS 2.0). "With this array, now built and operational in the Near Field Range, we're proceeding to plan and commencing full-scale integration and test of AMDR's unprecedented capability."

Subcontractor Major Tool and Machine delivered the array structure to Raytheon's Near Field Range on July 29; and Raytheon installed all passive RF components before September 1. The first Radar Modular Assembly (RMA) was powered up in October and testing began. All RMA chassis were installed by October 16, complete with cooling, power, fiber-optic control and data interfaces. In 79 days the array infrastructure was complete – verification of the simplicity of the AMDR array design. Population of the array with Transmit Receive Integrated Multi-channel Modules and Distributed Receiver/Exciter LRUs completed on December 16.

These recent achievements are among the many successes and milestones realized to date, including:

  • Nine of nine major program milestones completed on schedule, including hardware and software Critical Design Reviews and the Development Test Event 2 (DT-2) Readiness Review
  • Transition to DT-2 - currently in process, culminating in 2016 with verification of hardware level specifications to requirements and shipment of the array to the Pacific Missile Range Facility in Hawaii for system validation testing (DT-3)
  • Completed Build 2 software early, with all planned functionality (30 capabilities), formally qualified in July 2016; Build 3 is more than 75% percent complete
  • 95% of EMD hardware production is complete; awaiting final power systems delivery in early 2016

Share

Print


Suggested Items

Lab Tests Armored Vehicles with Auto Industry 'Dummies'

07/25/2016 | U.S. Army
In an unassuming warehouse on Aberdeen Proving Ground, Maryland sit nearly 50 men in uniform, waiting for their mission during an upcoming test event. They're sporting Army Combat Uniforms, standard-issue boots, a crane hook protruding from their heads, and a plethora of color-coded wires spilling out the back of their necks.

FLA Program Takes Flight

02/15/2016 | DARPA
They may not have zoomed flawlessly around obstacles like the Millennium Falcon did as it careened through the hull of a crashed Star Destroyer in Star Wars VII. But the sensor-loaded quadcopters that recently got tested in a cluttered hangar in Massachusetts did manage to edge their way around obstacles and achieve their target speeds of 20 meters per second.

Mr. Laminate Tells All: Who Would Like a Mil-Spec Audit?

01/05/2016 | Doug Sober, Essex Technologies Group
I remember when IPC-4101 was completed and released in December 1997 and the question came up “should IPC create a policeman program to enforce it?” To a person that helped create IPC-4101, absolutely no one wanted such an audit program ever again. Including me and the IPC staff liaisons. Maybe we should have rethought that position.



Copyright © 2021 I-Connect007. All rights reserved.